 |
|
LWT
remote control dredge at
Fernald, Ohio Super Fund site
(Model
RCLPE)
|
When
the operations manager at the Fernald, Ohio Super Fund
Site Remedial Action Project needed a dredge to
remediate sludge from one of four on-site waste (raffinate)
pits, they required more than the usual dredging
standards. The dredging operation was complicated with
the possibility of unknown radon emissions, chemical
contamination, and radiation that could be unleashed as
material was dredged.
The
Super Fund nuclear waste project will require removal of
sludge from on-site waste pits and from a facility for
chemical stabilization and solidification of the
low-level radioactive sludge. The project is funded up
to $1 billion and scheduled for completion by the year
2001. Cleanup is being conducted by the Morrison Knudsen
Corp. of St. Charles, MO, in cooperation with Jacobs
Engineering.
|
|
|
Hand
held radio
remote control
|
The
pits contain low-level radioactive "raffinate"
debris and sludge. It was important that the
contaminated sludge be kept wet to keep radon particles
from becoming airborne, and to minimize inhalation or
ingestion of radon. By using underwater dredging
equipment and pumping the sludge through hoses to the
processing operation, the mixture could remain wet and
the contamination enclosed throughout the operation.
The
solution to the Fernald requirements lay in the
implementation of a remote controlled dredge. Shore
control would eliminate operator exposure since the
dredge could traverse the pit using a system of cables
and winches keeping the operators a safe distance from
the pit. The dredge would also have to be equipped for
on-board operation.
Morrison
Knudsen made the decision to purchase a dredge from
Wisconsin-based Liquid Waste Technology LLC The company
designs and builds the Pit Hog™ line of dredging and
pumping equipment for removal of sludge, sediment, and
residuals. The company’s floating dredges have been
successfully used on automated sludge removal systems at
wastewater treatment plants, power plants, petroleum
refineries and other commercial and municipal facilities
that require lagoon pumping.
Two
months later, a Pit Hog™ remote control dredging
system was launched. The dredge implemented at Fernald
utilizes an Allen Bradley programmable logic controller
(PLC) to direct its traversing movements, depth and rate
of pumping. Engineers at Liquid Waste Technology
programmed the PLC so that it arrived "custom
tailored to suit our needs and meet our
requirements," said Bruce Fox, project operations
engineer.
There
are a total of four on-site waste pits scheduled for
cleanup. The Pit Hog™ dredge can be transported from
pit to pit as needed. The initial dredging operation was
performed in raffinate pit 3.
On-site
testing was performed over a period of three weeks to
evaluate the Pit Hog's™ effectiveness. The engineers
were surprised by this particular dredge’s
performance. Design engineers had estimated the range of
percent solids delivered in the discharge slurry to
between 5% and 20% solids. The Pit Hog™ dredge
exceeded those expectations.
According
to Fox, the dredge pumped between 16% and 22.6% solids
rather than the expected 15% solids slurry. On average,
a 20.1% solids content slurry with an average unit
weight of 71.8 lbs/cu.ft. was pumped. Flow rates were
estimated at 450 gpm slurry flow through 300’ of 4-in
connecting hose with aluminum floats.
On-site
disposal will be accomplished by transforming the sludge
into grout, which will subsequently be used to fill
voids in debris from destroyed uranium refining
buildings. There are 40 "disposal cells" at
the 220 acre site which are filled with rubble.
The
liquid grout made from the sludge will be poured into
cells, surrounding the rubble and preventing the
settling of debris in the cells while at the same time
disposing of the dredge waste. According to John Enger,
project manager, "waste pit dredging is a preferred
method when waste is treated and disposed of
on-site." The treatment, called chemical
stabilization and solidification mixes the sludge with
20% to 25% solid including flash (calcium oxide ash) and
cement for a grout consisting of about 20% to 25%
solids.
|