|
Dredging
at Weldon Spring Super Fund Project
Radioactive
Sludge at Weldon Spring Super Fund Project Removed by LWT Remote
Controlled Dredges
Remote
controlled Dredging proved to be the best method of removing
radioactive sludge from settling ponds of a former uranium
processing plant near St. Charles, Missouri. Dredging keeps the
material wet and out of contact with the atmosphere throughout
the removal and treatment process, eliminating the danger of
contaminates becoming airborne.
The
Weldon Spring Site Remedial Action Project (WSSRAP) is a
Superfund site that was designated a Major Project for control
and decontamination in May 1985. Funding of up to $1 billion has
been allocated for this site, which consists of four waste (raffinate)
pits, a facility for chemical stabilization and solidification
of low level radioactive sludge.
In
1984, scientists from Argonne National Laboratory were retained
to evaluate the contaminates at the former uranium processing
facility and to recommend a way to handle and dispose of the
waste. Argonne is a research facility operated by the University
of Chicago in the suburbs west of Chicago.
Mary
Picel, an environmental health scientist at Argonne, has worked
the project since 1993.
|
|
|
LWT
RCLPE Dredge on
Super Fund Pond
|
"We
determined that the best way to move the material was to dredge
it, grout it and bury it," said Picel. The disposal cell is
30 feet deep with clay to prevent migration of contaminants
through to the groundwater. A million and a half cubic yards of
contaminated materials are being placed in the cell. Besides
186,000 cubic yards of grouted raffinate, this includes wood and
metal debris, process equipment, piping and construction
materials. About 6,130 drums containing PCB-contaminated oils,
asbestos insulation, uranium wastes, magnesium compounds,
graphite and sediment were samples, repackaged and placed in
storage until final placement in the disposal facility. The pit
will be capped with rubble and soil, which will be an effective
shield, said Picel. The area will be continuously monitored for
radon.
Two
Liquid Waste Technology (LWT) Electric Remote Control Lagoon
Pumpers, (RCLPE's) custom built at 34 feet long and the standard
101 inches wide for extremely shallow draft, were purchased by
project owner, the Department of Energy, in addition to another
smaller dredge which was used in a pilot project to test the
dredging and processing technique.
The
dredging portion of this massive cleanup project consisted of
removing 122,000 cubic yards of sludge from the raffinate pits
and pumping it to a CSS (chemical stabilization and
solidification) facility. More than 75 million gallons of water
with an average of eight to 10 percent solids was pumped to move
the sludge from the pits to the treatment plan. The sludge was
screened for oversize materials, then thickened with a polymer
before it was blended with Portland cement and fly ash and
transferred as grout to the disposal cell. About 180,000 cubic
yards of grout was produced.
More
than 25,000 cubic yards of sludge was treated in situ in pit 4,
then excavated and transported to the disposal facility.
|
|
|
PLC
Controlled LWT Dredge at Weldon Spring Site
|
MK-Ferguson
with Jacobs Engineering Group, Inc., as its integrated
subcontractor, is the Project Management
Contractor
(PMC). MK's responsibilities include procurement and management
of remedial construction services; site maintenance,
surveillance, security; characterization, analysis, and
engineering services; planning, budgeting, and reporting; and
integration of cost and schedule for all participants.
MK-Ferguson is a major subsidiary of Morrison Knudson
Corporation of Boise, Idaho. The company's WSSRAP Project
Director is Douglas E. Steffen.
|
|
|
Dredge
Remote Controlled Operating Station for LWT Pit Hog™
Dredge
|
Matt
Myers is MK project supervisor. The dredging portion began in
April 1998 and was completed by the end of the year, he said.
Two dredges were purchased to ensure continued operation should
one shut down, said Myers. Dredging continued around the clock,
seven days a week from start to finish, with four three-person
crews, all members of the AFL-CIO Operating Engineers Union.
All
personnel on the project were required to wear Level B
protective clothing. No personal clothing was worn on the site.
Workers dressed in hospital pants and shirts and disposable
cotton coveralls, cotton socks and 16-inch rubber boots, hard
hats and safety glasses. Though the dredge was designed for
remote operation, the management opted for on-board operation,
and the dredge operator wore a disposable Syranex waterproof
coverall.
At
the end of the shift, the crews would remove all clothing, pass
through a personal contamination monitor and into a shower
facility before donning their street clothes.
The
dredges are 125 hp machines with eight foot, two inch augers.
Steel I-beams at the ends of the ponds provide stabilization for
winching forward and back, and trolleys move the dredge
laterally at the end of a cut. A triple-sheave traverse winch is
mounted on deck on an elevated stand, which holds the travel
cable well off the water surface. The cable is shrouded along
the length of the deck.
An
electric motor drives a pressure-compensated hydraulic pump
providing constant hydraulic pressure for all functions. A
pressure relief valve prevents damage or blown fuses in the
event of over-power or junction blockage.
The
rubber-lined pump is an eight-inch by eight-inch
recessed-impeller centrifugal pump.
Source:
International Dredging Review
|